U2-L2-P1
Introduction: The primary methods used in settling property insurance losses include: Actual cash value (ACV), replacement cost (RC) and valued or scheduled policy settlement.
Actual cash value (ACV): ACV is defined as replacement cost less depreciation. ACV is the most common method used in settling personal property insurance claims. However an insurer reserves the right to settle losses based on the lesser of the actual cash value (ACV) or the cost to repair or replaced the damaged property. Assume a five year old couch cost $2,000 to replace and the depreciation value was $500. The ACV would equal $1,500 ($2,000 - $500).
Broad evidence rule: The broad evidence rule is an alternate method used by courts and states in determining ACV. It states that in determining ACV all applicable and relevant information an expert would use should be considered to determine the property actual cash value.
Replacement cost (RC): RC is defined as the cost to replace the damaged property with property of like kind and quality. Generally RC is settled on an ACV basis and any remaining settlement amount is payable when the insured provides proof that the damaged property was replaced. Some states require that a policy subject to a replacement cost settlement that the replacement cost of a dwelling be paid up front prior to the repair of the damaged property without reduction for depreciation but subject to the limits of the policy.
Valued policy settlement: A valued policy settlement pays the actual amount of insurance on the property in the event of a total loss, regardless of the property ACV or RC. The value of the property is agreed upon by the insurer and insured prior to the contract date. Generally an appraiser is used to determine the value of the property being insured.
Valued policy law: Some states have a valued policy law that requires an insurer to pay the full amount of insurance on a dwelling when there is a total property loss.
The following question is part of this page, answer it and then click below to check for your response:
Which settlement method is defined as replacement cost less depreciation?